AI DC Calculator Kingdom of Saudi Arabia

How much power, water and land does an AI data centre really need?

An interactive planning calculator for AI data centre infrastructure in Saudi Arabia — sizing electricity demand, generation capacity, cooling, water, land, GPUs and emissions from first-order engineering relationships, with every assumption sourced and stated.

PUE-driven model SERA tariff 0.18 SAR/kWh Grid EF 0.568 kg CO₂e/kWh NVIDIA H100 → Vera Rubin
Saudi peak demand
≈ 80 GW (2025–26 expected)
National demand 2030
365.4 TWh projected
National DC strategy target
~1.5 GW by 2030 (MCIT/SDAIA)
Mode A

Large AI Data Centre — above 100 MW

For companies and investors establishing large, purpose-built AI campuses. Start from the critical IT load and the model sizes the full facility: grid demand, generation equivalents, cooling, water, land, GPU fleet and emissions.

Power & Energy

IT load Cooling & facility overhead
Total facility powerIT load × PUE — demand at the fence
MW
Cooling & facility overhead
MW
Annual energy consumptionfacility power × 8,760 h × utilization
TWh/yr
Annual IT energy
TWh/yr

Electricity Cost

Annual electricity costat SERA cloud-computing tariff
SAR M/yr
Monthly electricity cost
SAR M/mo

Compute

All-in power per GPUTDP × server overhead × IT infra overhead
W/GPU
Number of GPUs
GPUs
Racks / server units
units

Land

Campus land area
hectares
  equivalent
  equivalent
km²

Cooling & Water

Cooling capacity≈ total facility power in thermal terms
kWth
Refrigeration equivalent
tons
Annual water consumption
m³/yr
Daily water consumption
m³/day

Grid & Generation

CCGT equivalentfirm gas capacity incl. T&D losses + reserve margin
MW nameplate
Solar PV equivalentenergy-equivalent nameplate, not firm
MW nameplate
Solar land area
km²
Grid connection voltage

Emissions & National Context

Annual CO₂ emissionsat Saudi grid emissions factor
t CO₂e/yr
Share of Saudi peak demandvs ≈80 GW national peak
%
Mode B

Small AI Data Centre — below 100 MW

For companies and entities upgrading or right-sizing an existing facility. Start from the number of GPUs you plan to deploy and the model sizes power, racks, cooling, floor space, cost and emissions.

Power

Total IT powerGPUs × TDP × server overhead × IT infra overhead
kW
Facility powerIT power × PUE
MW
Servers / units
units
Number of racks
racks
Actual rack density
kW/rack

Cooling

Cooling capacity
kWth
Refrigeration equivalent
tons
Recommended coolingby actual rack density: >50 liquid · >25 hybrid · else air

Space

IT hall floor space
Total facility spaceIT hall × 2 for electrical, cooling, support rooms

Cost & Energy

Annual electricity cost
SAR K/yr
Monthly electricity cost
SAR K/mo
Annual energy
MWh/yr

Emissions

Annual CO₂ emissions
t CO₂e/yr
National Outlook

KSA 2030 Scenarios — Moderate vs High AI Growth

Two national-level scenarios for Saudi Arabia's data centre fleet in 2030, combining new AI capacity with the existing non-AI baseline. Scenario inputs are editable — outputs recompute live.

Editable scenario inputs for KSA 2030 — Scenario 1 Moderate vs Scenario 2 High AI growth
ParameterS1 · ModerateS2 · High

Computed national requirements, 2030

Scenario 1 assumes GB200-class hardware with hybrid cooling; Scenario 2 assumes B300/GB300-class hardware with closed-loop liquid cooling.

Metric
S1 · Moderate
S2 · High
Hardware

NVIDIA GPU Platform Reference

Platform power and configuration data used by the calculator, from NVIDIA datasheets (2024–2025) and SemiAnalysis system-power analysis. Server overhead captures CPUs, memory, NVLink/NVSwitch fabric, PSU losses and intra-server cooling.

GPU PlatformTDP (W)System ConfigSystem Power (kW)GPUs / UnitServer OH (×)Cooling Req.AvailabilityNotes

Assumptions & Methodology

Every figure this calculator reports is a first-order engineering estimate intended for capacity planning and policy discussion — not detailed facility design. Real requirements depend on site conditions, hardware generation, workload mix, cooling design and contractual terms. Validate against vendor engineering studies before committing capital. The model mirrors AI_DC_Calc_v5.xlsx and the accompanying report "Estimating Saudi Arabia's AI Data Center Requirements".

01Power Usage Effectiveness (PUE)1.5 default

Conventional AI-facility PUE for Saudi Arabia; a sustainable target would be 1.3. Mode B varies PUE by cooling: air 1.7, hybrid 1.5, liquid 1.3. Alshehri et al. (2025), KAPSARC/ICAIRE, Table B2, p. 62.

02Water Usage Effectiveness (WUE)0.15–1.8 L/kWh IT

By cooling type: air-cooled 1.8, hybrid 0.5, liquid-cooled 0.1–0.15 L/kWh IT. Microsoft Sustainability Report (2024); Google Environmental Report (2025); Spindler et al. (2024).

03GPU TDP & server overhead700–1,800 W · 1.35–1.82×

Per-platform TDP from NVIDIA datasheets. Server overhead (1.39× NVL72 racks, 1.82× DGX H100) covers CPUs, memory, NVLink/NVSwitch fabric, PSU losses and intra-server cooling. NVIDIA datasheets (2024–25); SemiAnalysis (2024), "100K H100 Clusters".

04IT infrastructure overhead1.1×

≈10% on top of compute for top-of-rack networking, storage and cluster-management servers. Industry convention; no single primary source.

05Utilization factor0.80 AI · 0.65 non-AI

75–85% is typical for AI training facilities; 50–70% for enterprise/colocation. Alshehri et al. (2025), Table B2, p. 62; Shehabi et al. (2024).

06Electricity tariff0.18 SAR/kWh

SERA cloud-computing tariff category (≈ $0.048/kWh); requires CST cloud registration and ≥80% annual load factor. The final dedicated data-centre tariff is not yet formally decided. SERA tariff schedule; Alshehri et al. (2025), §4.4, pp. 29–30.

07Land factor2,000–3,500 m²/MW IT

Liquid 2,000 / hybrid 2,500 / air 3,500 m² per MW IT. Real projects span ~1,000–9,000 m²/MW — anchors: Khazna Dammam ≈1,125 (DCD, 2025); Applied Digital Ellendale ≈9,100. Defaults are a hyperscale midpoint.

08Generation capacity factorsCCGT 0.85 · Solar 0.24

Saudi annual solar capacity factor runs 22–26%. Solar PV equivalent is energy-equivalent nameplate, not firm capacity. Solar land assumes ≈500 MW per km². KAPSARC Renewables Tracker (2025).

09T&D losses & reserve margin8% · 1.10×

Typical Saudi transmission & distribution losses are 6–9%; the Saudi Grid Code reports a planning reserve margin of 8–10%. IEA Saudi Arabia profile (2024); SEC Annual Report (2024); Saudi Arabian Grid Code (SERA, May 2024).

10Grid emissions factor0.568 kg CO₂e/kWh

Reflects the Saudi fossil generation mix of 41.2% oil + 58.2% gas. IEA Emissions Factors (2024); Alshehri et al. (2025), Appendix C, p. 63.

11National context anchors80 GW · 365.4 TWh

Saudi peak ≈80 GW (SEC reported 72.9 GW in summer 2024, ≈97% of national supply; ~80 GW reflects the expected 2025–26 peak). 2030 national electricity demand projected at 365.4 TWh. SEC 2024 Financial Results (2025); MEES (2024); Alshehri et al. (2025), Appendix B, p. 61.

12Cooling & conversion constants3.517 kWth/ton

Nearly all electricity consumed becomes heat, so cooling load ≈ total facility power in thermal terms. Refrigeration tons = kWth ÷ 3.517. Year = 8,760 hours. Mode B recommends liquid cooling above 50 kW/rack and hybrid above 25 kW/rack. Uptime Institute (2024); JLL (2024).

13Grid connection voltage33 kV → 380 kV

Indicative thresholds: ≥50 MW facility demand connects at 380 kV; 10–50 MW at 132 kV; below 10 MW at 33–69 kV distribution level.

14Scenario design (2030)2.0 / 4.1 GW IT

Scenario 1 (Moderate): 2,000 MW total IT load — 950 MW AI on GB200-class hardware with hybrid cooling. Scenario 2 (High): 4,100 MW — 3,050 MW AI on B300/GB300-class hardware, liquid-cooled. Both retain a 1,050 MW non-AI baseline at PUE 1.7 and 65% utilization.

References & Sources

1 — Saudi Government & Regulatory Sources
2 — Saudi AI & Data Centre Market
3 — Saudi Grid, Emissions & Energy
4 — PUE, Cooling & Sustainability
5 — GPU Hardware & CAPEX
6 — Water, Land & Regional Data